A recent blog post at the EMJ Construction website describes construction at the Fountains at Farah as "going at full tilt" with a target opening date of October 2013. EMJ Construction is the general contractor on the project.
|
Concrete beams will support the upper level of the parking structure. |
Over 300 workers are on site daily, according to the post, with 2500 to 4000 yards of concrete poured per week. According to the blog, the Fountains at Farah development is the "largest ground-up new retail project under construction in the state of Texas and west of the Mississippi River."
|
Retail shops and restaurants will line the front of the garage. |
EMJ Construction blog post:
http://www.emjcorp.com/blog/2012/12/fountains-at-farah-updatePreviously:
'Fountains' Progress Continues